Quality control

6 hold points6 inspection items

What we check, when, and who approves

ItemWhat we checkWhenWho approves
ExcavationLevel, bottom grading and preparationBefore blindingConsultant's engineer
WaterproofingOverlaps, bonding, corners and jointsBefore backfilling or rebarConsultant's engineer
FormworkDimensions, alignment, fixing and clean surfacesBefore pouringConsultant and main contractor
Reinforcing steelDiameters, spacing, cover and lapsBefore pouringConsultant and main contractor
ConcreteMix conformity, samples and curing after pouringDuring and after pouringMain contractor and laboratory
Plaster and blockworkFlatness, corners and alignmentBefore final finishingConsultant's engineer

Execution stages and hold points

  1. Site takeover

    Hold pointMethod statement approval
  2. Excavation and blinding

    Hold pointBottom level acceptance
  3. Waterproofing

    Hold pointWaterproofing inspection
  4. Formwork and rebar

    Hold pointConsultant acceptance before pouring
  5. Pouring and curing

    Hold pointConcrete samples during pouring
  6. Striking and handover

    Hold pointFinal acceptance
Pouring after acceptance

Planning and follow-up

DocumentWhenPurpose
Work planWeeklyWork fronts, crews and planned pours, coordinated with the main contractor's schedule
Method statementBefore each item startsFor consultant approval before execution
Inspection requestBefore every pour or cover-upAcceptance of rebar, formwork and waterproofing by the consultant's engineer
Daily reportDailyManpower, executed quantities and any obstacles
Quantity surveyMonthlyExecuted and approved quantities, the basis for the payment certificate
Comments logOngoingTracking the consultant's comments until closed
Handover recordAt handoverHanding over completed works to the main contractor